PMP Question 10


The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:


A. Plan Schedule Management.
B. Develop Project Charter.
C. Develop Schedule.
D. Plan Scope Management.

Correct Answer: A