QUESTION 28
The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:
A. Planning.
B. Executing,
C. Monitoring and Controlling.
D. Closing.
Correct Answer: C
PMP Exam Dumps Questions
Thursday 1 December 2016
Saturday 26 November 2016
PMP PMI Exam Dumps Questions Answers
QUESTION 27
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
A. Interrelationship digraphs
B. Tree diagram
C. Affinity diagram
D. Network diagram
Correct Answer: B
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
A. Interrelationship digraphs
B. Tree diagram
C. Affinity diagram
D. Network diagram
Correct Answer: B
Friday 25 November 2016
Latest PMI PMP Exam Dumps
QUESTION 26
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
A. Interactive communication
B. Claims administration
C. Conflict management
D. Performance reporting
Correct Answer: B
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
A. Interactive communication
B. Claims administration
C. Conflict management
D. Performance reporting
Correct Answer: B
Friday 18 November 2016
PMI PMP Exam Study Material
Question 25
Which item is an input to the Define Activities process?
A. Schedule data
B. Activity list
C. Risk register
D. Scope baseline
Correct Answer: D
Which item is an input to the Define Activities process?
A. Schedule data
B. Activity list
C. Risk register
D. Scope baseline
Correct Answer: D
Tuesday 2 August 2016
PMI PMP Exam Study Material
Question 24
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
A. 0.50
B. 0.67
C. 1.50
D. 2.00
Correct Answer: A
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
A. 0.50
B. 0.67
C. 1.50
D. 2.00
Correct Answer: A
Wednesday 27 July 2016
PMI PMP Exam Questions
Question 23
A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:
A. Adaptive
B. Predictive
C. Incremental
D. Iterative
Correct Answer: B
A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:
A. Adaptive
B. Predictive
C. Incremental
D. Iterative
Correct Answer: B
Wednesday 4 May 2016
PMP PMI Exam Dumps Questions Answers
PMP Question 22
Scope, schedule, and cost parameters are integrated in the:
A. Performance measurement baseline.
B. Analysis of project forecasts,
C. Summary of changes approved in a period,
D. Analysis of past performance.
Correct Answer: A
Scope, schedule, and cost parameters are integrated in the:
A. Performance measurement baseline.
B. Analysis of project forecasts,
C. Summary of changes approved in a period,
D. Analysis of past performance.
Correct Answer: A